Display Key Tasks in Microsoft Project’s Timeline View
by Avantix Learning Team | Updated July 8, 2016
Applies to: Microsoft® Project® 2010, 2013 and 2016 (Standard and Professional)
Timelines are a great way to view key tasks and milestones in a project. You can add tasks to a timeline and then format it any way you’d like. The Timeline View is available in Microsoft Project 2010 and later versions and displays by default. You can add and remove items from a timeline and copy a timeline into an email or Word or PowerPoint file to present the timeline. In this article, we’ll focus on a single timeline (although Project 2016 now supports multiple timelines and you can create views with different timelines).
Recommended article: 10 Timesaving Shortcuts in Microsoft Project’s Gantt Chart View
Below is a sample project with a timeline which includes summary and milestone tasks:
Displaying the Timeline View
The Timeline View is displayed by default when you first install Project. However, you can turn the Timeline View off and on using Options or by selecting Timeline on the View tab in the Ribbon:
Working with Timeline Tools
When you click in the timeline, a Timeline Tools Format tab appears with options for the timeline.
In order to work with just the timeline and not move the Gantt Chart, turn off Pan & Zoom in the Show/Hide group.
Adding single tasks to a timeline
To add single tasks to a timeline:
- Right-click on a task and then select Add to Timeline from the menu. Alternatively, click on the Add to Timeline button on the Task tab in the Ribbon.
- Repeat this for each task or milestone you want to add.
Adding multiple tasks to a timeline
To add multiple tasks to a timeline:
- Click on the ID of the first task.
- Control-click on the IDs of subsequent tasks.
- Right-click on one of the selected tasks and select Add to Timeline. Alternatively, click on the Add to Timeline button in the Properties group on the Task tab in the Ribbon.
Tip: timelines can work well if you add only summary tasks and milestones to the timeline.
If you want to add just milestone and summary tasks, you could filter to display milestone and summary tasks first and then repeat the steps above to add these tasks to the timeline.
Removing tasks from a timeline
To remove tasks from a timeline:
- Click once on the bar, diamond or callout text in the timeline that you wish to delete.
- Select Remove from Timeline in the Timeline Tools Format tab or right-click on the item and select Remove from Timeline. You can also simply press Delete.
Displaying tasks as callouts in a timeline
Initially, tasks are displayed as bars on a timeline. To display tasks as callouts:
- Click on a task in the timeline.
- Click on the Timeline Tools Format tab and then select Display as Callout. You can also right-click on the task and select Display as Callout from the menu. The task now points to the timeline from above or below the timeline. You can then drag the task to the desired location.
If you want to change a callout to a bar again, click on the callout and then click on Display as Bar on the Format tab on the Ribbon to turn it back into a bar. You can also right-click on the task and select Display as Bar from the menu.
Below is a timeline with summary tasks as callouts:
Adding rows in a timeline
To add rows in a timeline:
- Click on a bar task in the timeline.
- Drag tasks up or down within the timeline to show them on different rows.
Changing colors in a timeline
To change colors in a timeline:
- Click on the task you want to change in the timeline. To select multiple tasks, Control-click on each task.
- On the Timeline Tools Format tab, click on Background/Fill or Font Color and select a color.
Changing the date format
To change the date format:
- Click anywhere on the timeline.
- Click on Timeline Tools Format tab and then click on Date Format.
- Select the desired format from the drop-down menu.
Sharing a timeline in an email, PowerPoint presentation or Word document
To share a timeline in an email, PowerPoint presentation or Word document:
- Click anywhere in the timeline.
- Click on the Timeline Tools Format tab and select Copy Timeline. A drop-down menu appears.
- Select For E-mail for a small size which is best for an email message. Select For Presentation for a medium size which is designed to work in a PowerPoint slide. Select Full Size for a large size which is the same size as it appears in Project.
- Paste the timeline by pressing Control + V in an email or file in Word or PowerPoint.
Printing a timeline
To print a timeline:
- Drag the line below the timeline to the bottom of the screen.
- Select File and then Print.
- Choose the desired print options and click on Print.
- To return to the split view, click on the View tab on the Ribbon and then select Timeline.
Subscribe to get more articles like this one
Did you find this article helpful? If you would like to receive new articles, join our email list.
Recommended Microsoft Project training courses
Microsoft Project: Introduction
Microsoft Project: Intermediate / Advanced
Microsoft Project: Introduction to VBA (Visual Basic for Applications)
Microsoft Excel: Intermediate / Advanced
Our instructor-led classroom training courses are delivered at our downtown Toronto location at 1 Yonge Street, Suite 1801 (Toronto Star Building), Toronto, Ontario, Canada (some courses may also be delivered at an alternate downtown Toronto location). Contact us if you’d like to arrange custom training at your office on a date that’s convenient for you.
To request this page in an alternate format, contact us.
Copyright 2019 Avantix® Learning Inc.
You may also like
10 Microsoft Project Shortcuts to Zoom and Move Quickly in the Gantt Chart Timescale
Zoom in, out and move using these great shortcuts in the Microsoft Project Gantt Chart timescale. The timescale in the Gantt Chart view appears on the right side and displays units of time.
Auto vs Manual Scheduling in Microsoft Project
In newer versions of Microsoft Project, you have the option of scheduling tasks using manual or auto scheduling. In earlier versions, Microsoft Project used auto scheduling which takes advantage of Project’s scheduling engine to schedule tasks.
10 Microsoft Project Tips for Working Efficiently in Tables
Tables are a core component of Microsoft Project. They appear in many views and display specific fields available in Project. The default tables that appear in the Tables drop-down menu on the View tab include …